GUAY is proud to have participated in a project that will transform Montreal’s urban landscape by installing a covered footbridge connecting the Royalmount real estate and commercial development to the De La Savane metro station. This project, located in the Midtown area, was carried out in two phases and required one of the largest conventional crawler cranes in North America.
Phase One: Installation of the eastern section of the footbridge, weighing approximately 143,300 lbs. Several steps and multiple cranes were involved, including assembling two 93,000 lb pieces with two 45-ton Liebherr LTC1050 3.1 all-terrain cranes. The final assembly took place in the parking lot of Rib’N Reef restaurant in Montreal in January, using a 350-ton Grove GMK 6350L-1 crane. A 650-ton Liebherr LTM1500 8.1 crane then transported the section to the site, where a 600-ton Terex AC500-2 crane completed the installation on February 2, 2024.
Phase Two: Installation of the western segment, the longest section, weighing nearly 378,000 lbs. This required a 700-ton Demag CC2800-1 crawler crane and a custom platform for the crane to move during the operation. The work took place at night and required the complete closure of the Décarie Expressway in Montreal.